4.6.13. After holes are connected and before connection to the lead wires, each series of electric blasting caps and all parallel series must be tested with an approved firing galvanometer.
R.R.Q., 1981, c. S-2.1, r. 6, s. 4.6.13; O.C. 1959-86, s. 58.